Home / Customer Portal / Business Application Services Essentials / Publications / Business Application Services (CORE) Executive Board - May 3, 2010

Business Application Services (CORE) Publications - Executive Board Meeting May 3, 2010

The following is a text transcript of the presentation made at the BAS (CORE) Oklahoma Executive Board meeting in May 2010.

Slide 1

BAS Executive Board May 3, 2010
Next CEB Scheduled - June 2, 2010

Slide 2

Agenda

  • SQL Requests/Problem Management Summary
  • Completed Projects
  • Portfolio
    • Budget Status
    • Priority
    • Execution Delivery Schedule
  • Projects in Movement
  • Program Status
    • HCM
    • Financials
  • Application Development Service Request Summary
  • Scorecard
  • Executive Issues

Slide 3

Problem Management

SQL Requests in Total April 2009 to March 2010
  April 2009 May 2009 June  2009 July 2009 Aug 2009 Sept 2009 Oct 2009 Nov 2009 Dec 2009 Jan 2010 Feb 2010 March 2010
ARBI 0 0 0 0 0 0 0 1 0 0 1 0
CRM 2 0 0 0 0 0 0 1 0 0 0 0
DBA/System 0 0 0 0 0 0 0 0 0 0 4 0
Procurement 8 3 9 4 1 5 2 0 0 0 0 0
HRMS 18 10 11 7 24 13 10 3 6 10 12 14
Financial 28 14 16 15 14 10 4 14 8 8 6 0
Financials 0 0 0 0 0 0 0 0 0 0 0 1
EPM 2 4 1 2 0 1 0 0 0 1 0 0
ELM 0 0 0 0 1 0 0 0 0 0 0 0
Purchasing 0 0 0 0 0 0 0 0 4 8 0 0

Legend

  • ARBI - Accounts Receivable/Business Intelligence
  • CRM - Customer Relationship Management
  • HRMS - Human Resources Management Systems
  • EPM - Enterprise Performance Management
  • ELM - Enterprise Learning Management
  • DBA/System - Database

Slide 4

Problem Management Summary
Summary Total Problems Resolved or Resolution in Process Investigating Resolved by Future Functionality DR to be Created Monitor
Financial 11 4 1 4 1 1
PO 2 2 0 0 0 0
HCM 13 10 0 0 3 0
DBA/System 2 0 1 0 0 1
Total 28 16 2 4 4 2

Slide 5

Completed Project, since last BAS Executive Board

Asset Management Pilot, Schedule (Green); Budget (Green)

 

Slide 6

Portfolio Priority 1-14
Project Name Project Manager Dept Function Current Project Phase Priority within Function
Backfill Developers for Production Support and Enhancements Fred Cantrell BAS Financial Mgmt + Human Capital Mgmt Execution 1
Time and Labor Pilot Alex / Kim BAS Human Capital Mgmt Execution 2
Commitment Accounting - Rollout Michael Grisser BAS Human Capital Mgmt Execution 3
Asset Mgmt - Pilot Alex / Kim BAS Assets Execution 4
Grants, Projects, Contracts, AR Billing - Oklahoma Department of Transportation /Oklahoma Economic Security Commission (ODOT/OESC) Alex / Kim BAS Enterprise Service Automation Execution 5
Time & Labor Manager Self Service ODOT Pilot Alex / Kim BAS Enterprise Service Automation Execution 6
People Soft Extract Staging Environment Lisa McKeithan BAS Other Execution 7
Inventory Pilot Department of Mental Health Alex/Kim BAS Supply Chain Management Execution 8
AP Workflow Michael Grisser BAS Financial Mgmt Planning, Execution 9
Higher Education Interface Lisa McKeithan BAS Human Capital Mgmt Planning, Execution 10
HCM Functionality Enhancements Michael Grisser BAS Human Capital Mgmt Execution 11
Inventory - ODOT Alex / Kim BAS Supply Chain Mgmt Execution 12
Grants, Projects, Contracts, AR Billing, ODOC/DEQ Alex / Kim BAS Enterprise Service automation Planning, Execution 13
Business Intelligence, Financials Analytics Lisa McKeithan BAS Other Planning 14

Slide 7

Portfolio Priority 14-26
Project Name Project Manager Dept Function Current Project Phase Priority within Function
Employee Self Service Rollout Michael Grisser BAS HCM Execution 15
Travel & Expense EFT Steve Wilson DCAR Financial Mgmt Execution 16
OpenBooks Phase III Lisa McKeithan BAS Other Planning 17
Asset Mgmt - Rollout Michael Grisser BAS Assets Planning, Execution 18
Grants - Provisioning Lisa McKeithan BAS Other Planning 19
Licensing Lisa McKeithan BAS Other Planning 20
Treasury General Ledger Implementation Alex BAS Financial Mgmt Execution 21
eBill Payment Lisa McKeithan BAS Financial Mgmt Concept 22
BI - CAFR Lisa McKeithan BAS Other Concept 23
Scanning and Bar-coding for Phase II modules Alex BAS Assets Concept 24
DCS Vendor Registration Lisa McKeithan BAS Supply Chain Management Execution 25
EFT Remit Advices Lisa McKeithan BAS Accounts Payable Planning, Execution 26
Federal Funding Accountability and Transparency Act (FFATA) Lisa McKeithan BAS Accounts Payable Concept 27
PeopleTools 8.49 Mike Jorski AppDEV FIN + CRM + EPM Initiation, Planning 28

Slide 8

Projects in Execution Delivery Schedule

  • HCM Funtionality Enhancements - January 2010-May 2010
  • EFT Remit Advices - April 2010-June 2010
  • PS Extract Staging Environment - January 2010-June 2010
  • Commitment Accounting Rollout - September 2009-June 2010
  • Backfill Developers - June 2009-June 2010
  • Inventory Pilot Department of Mental Health - April 2010-July 2010
  • ODOT/OESC Grants/Projects/Contracts/Accounts Receivable/Billing - July 2009-July 2010
  • Inventory ODOT - August 2009-July 2010
  • Time & Labor MSS ODOT Pilot - March 2010-July 2010
  • Time & Labor Pilot - June 2009-July 2010
  • DCS Vendor Registration - December 2009-August 2010
  • Treasury General Ledger Implementation - April 2010-December 2010
  • Grants/Projects/Contracts/Accounts Receivable/Billing Time & Labor Extended, Commerce, Department of Environmental Quality - March 2010-December 2010
  • Asset Management Rollout - April 2010-August 2011
  • Higher Education Interface - May 2010-October 2011

Slide 9

Detailed Milestone Plan, BAS - 2602 AP Workflow

The project will focus on a basic implementation of workflow for the Accounts Payable (AP) module for pilot agencies ODOT, OESC and Office of State Finance (OSF). ODOT and OESC will enter vouchers into control groups and submit the vouchers for workflow approvals. there will be a maximum of three workflow approval steps.

Milestone Plan (+/- 10%)

  • Fits/Functional Design. (Task, April-May 2010)
  • Technical development. (Task, May 2010)
  • Functional build/role mapping. (Task, May 2010)
  • Integration testing. (Task, June 2010)
  • Prepare for and conduct User Assisted Testing (UAT). (Task, June 2010)
  • Production setup. (Task, June-July 2010)
  • Go live. (Milestone, July 2010)

Issues

  • Immediate approval required to meet dates.
  • State resources to be identified and confirmed.

Slide 10

Detailed Milestone Plan,  2676 - OpenBooks Phase III

Design and build the OpenBooks data warehouse and website. New design must include improved search functionality including detailed vendor payment dashboard look and feel, and download capabilities.

Milestone Plan (+/- 50%)

  • Design and build extracts to data staging environment. (Task, April-May 2010)
  • Design data warehouse. (Task, May-June 2010)
  • Design website. (Task, May-July 2010)
  • Build website. (Task, June-September 2010)
  • Deploy. (Milestone, October 1, 2010)

Issues, Assumptions

  • Schedule includes interruptions for staff functions including training, ARRA reporting period, etc.
  • AP workflow will delay this timeline.
  • Financials Analytics will not start until after this project is completed.

Slide 11

Detailed Milestone Plan, AppDev-2611 PeopleTools 8.49

Upgrade the BAS FIN, CRM & EPM systems to PeopleTools 8.49. See notes below as this project now only includes the PeopleTools upgrade in the application.

Milestone Plan (+/- 10%)

  • Prepare change assistant and stage software - 2 days. (Task, August 2010)
  • EPM non-production environments (dmo, tst, qa) & test - 3 weeks. (Task, August-September 2010)
  • EPM production - (prd) 1 day. (Task, September 2010)
  • EPM development (dev) - 2 days. (Task, September 2010)

Issues

  • CRM will de done with the CRM ITIL project (when?)
  • EPM will be done separately. September is earliest it can be started due to seasonal business activity.
  • FIN will be done with the 2010 Bundle project

Slide 12

Program Status

HCM

Slide 13

BAS – 1080 Higher Education Payroll

  • Status: Green
  • Convert higher education agencies from the legacy payroll system to the PeopleSoft system.
Key Activities
Task Start End
System Testing - test script preparation and validation and system testing 5/32010 8/31/2010
User Acceptance Testing - includes conversion and parallel runs for the University of Oklahoma (OU) 9/1/2010 15/15/2010
Production preparation 10/16/2010 10/31/2010
Production - OU 11/1/2010 11/1/2010

 

Requires Awareness:
  • Statement of Work (SOW) has been signed and Purchase Order (PO) prepared.
  • OU will be the pilot agency and will participate in all testing phases. UAT will consist of running conversion process and parallels for OU which should provide final sign-off on system readiness. OU is unavailable during parts of August and September due to extra workload for fall semester.

Slide 14

BAS – 2581 Time and Labor

  • Status: Integration testing complete for OESC. UAT in progress. Integration Acceptance awaiting ODOT.
Key Activities
Task Start End
UAT - OESC & Statewide 4/12/2010 4/30/2010
Intgration Testing - ODOT (see awareness) 4/19/2010 5/14/2010
System Roll - OESC 5/3/2010 5/16/2010
Go Live - OESC   5/17/2010
UAT - ODOT 5/24/2010 6/18/2010

 

Requires Awareness:
  • BAS integration has not started.

Slide 15

BAS – 2636 Commitment Accounting Rollout

  • Status: GREEN
  • Roll out plan is progressing as scheduled. Group F successfully converted and payrolls processed. Group G being prepared for the May roll out.
Key Activities
Task Percentage Complete Start Finish
Group F Roll Out 100 1/21/2010 4/30/2010
Group F Question & Answer (Q&A) Session 100 3/16/2010 3/16/2010
Group G Q&A Session 100 4/13/2010 4/13/2010
Group G Roll Out 25 2/8/2010 5/30/2010
Group H Q&A 0 4/26/2010 4/26/2010
Group G Training 0 4/26/2010 4/29/2010
Group G Conversion 0 5/15/2010 5/16/2010
Group H Conversion 0 5/22/2010 5/23/2010
Group I Conversion - Human Resource data only 0 6/5/2010 6/6/2010

 

Requires Awareness:
  • No issues at this time.

Slide 16

Commitment Accounting Rollout Statistics

Group Conversion Date Agencies Number of Employees
A 9/15/2009 5 4,230
B 12/13/2009 19 3,812
C 1/16/2010 14 3,885
D 2/13/2010 18 3,393
E 3/13/2010 8 5,493
F 4/17/2010 43 5,000
Total Live   107 25,813
       
G 5/15/2010 19 5,125
H 5/22/2010 1 8,571
I 6/5/2010 1 526

Slide 17

BAS – 2667 HCM Functionality Enhancements

  • Status: GREEN
  • All Functional specs are completed. All Technical specs are completed. Enhanced Search Match is complete and has been released to all system users. Salary Survey are in User Acceptance Testing. SQR reports are still being developed and tested.
Key Activities
Task Percentage Complete Start End
ODOT - Completed Location table updates as well as updates to job and position with the new locations 100 1/1/2010 1/15/2010
Enhanced Search Match 100 3/1/2010 4/15/2010
Salary Surveys 80 1/1/2010 5/7/2010
Queries (71%) and Reports 80 1/1/2010 5/12/2010
Implement Badge Functionality 100 4/5/2010 5/14/2010

Slide 18

Service Catalog Requests - Employee Self Service Rollout

  Agencies Number of Employees
Live on systems as of 4/1/2010 94 25,663
Scheduled after 4/1/2010 16 3,591
Exempted/Legislative/Judicial 7 10,021
Total live/scheduled/exempted 117 39,275
To be completed/scheduled 11 439
Target 128 39,714

Slide 19

BAS – 2674 Manager Self Service ODOT / Pilot

  • Status: GREEN
  • Project will be in two phases: (1) limited salary personnel April 24 and (2) all non-Agile Asset personnel will go at same time as Projects go-live.
Key Activities
Task Percentage Complete Start End
Go-Live Limited Pilot 100 4/24/2010 4/24/2010
Requirements - Full Implementation 100 3/23/2010 4/7/2010
User Acceptance 0 5/24/2010 5/29/2010
Train the Trainer 0 5/24/2010 6/1/2010
Go Live 0 To Be Determined (TBD) TBD

 

BASSlide 20

Program Status

Financials

Phase II Modules

Slide 21

BAS – 2675 Data Staging Environment

  • Overall Issues Status: Green
  • Build staging environment containing PeopleSoft extracts that will be used by ODOT.
Key Activities
Task Start Finish ODOT Access
Development: Contracts (0513) and Project Costing (0514) are still in Development. 2/15/2010 5/14/2010 N/A
AP Alltrans (0287) - OSF Testing 4/19/2010 5/14/2010 4/28/2010
Deposit Alltrans (0515) - OSF Testing 4/19/2010 5/14/2010 4/28/2010
Vendors (0152) - OSF Testing 4/26/2010 5/28/2010  
AR/Billing (0512) - OSF Testing 4/26/2010 5/28/2010  
Assets (0523) - OSF Testing 4/26/2010 5/28/2010  
Purchase Orders (0234) - OSF Testing 4/26/2010 5/28/2010  
Production - GL alltrans (0188) & Setup Tables (02235) 4/26/2010 6/30/2010 4/28/2010

 

Requires Awareness: Gave Phil access to FSDEV so he has access to tables as soon as OSF staff does; he can begin his development/testing as we are testing.

Slide 22

BAS – 2680 EFT Remit Advices

  • Overall Issues Status: GREEN
  • Merkur has software that works with delivered PeopleSoft functionality to email remit advices to vendors for electronic payments. This alleviates the need for agencies to mail invoices that typically arrive several days after money is deposited into a bank account. This will streamline processing for vendors.
Key Activities
Task Start Finish
Finalize Contract and Requisition for Merkur 4/21/2010 5/21/2010
Configuration and Setup 5/31/2010 6/04/2010
Customization of Remit Advices 5/31/2010 6/4/2010
Testing 6/7/2010 6/11/2010
Production 6/14/2010 6/14/2010

 

Requires Awareness:
  • Will work with transaction Processing and Security teams to identify any necessary changes to the delivered remit advices so that it will meet state standards.

Slide 23

BAS - 2681 DCS Vendor Registration

  • Status: Green
  • Build interfaces between ok.gov and PeopleSoft for validation and upload of vendor bidder data into PeopleSoft.

 

Key Activities
Task Start Finish
Finalize SOW and Interagency Agreement 4/15/2010 4/23/2010
Development 4/19/2010 5/31/2010
Testing 5/10/2010 6/30/2010
Documentation 5/10/2010 6/30/2010

 

Requires Awareness:
  • Development request have been completed. Routing for signatures.
  • SOW (Innovativ) and DCS Interagency Agreement have been sent to DCS.
  • Development is in progress - ok.gov and Innovativ.

Slide 24

BAS – 2665 Asset Management Rollout   

  • Overall Issues Status: GREEN
  • Project approved in last CEB Meeting but will not make much progress until July after the DMH Inventory Implementation is completed.
Key Activities
Task Start Finish
Prepare for and conduct project kick off TBD TBD
Configure and verify agency conversion data 7/16/2010 10/5/2010
Perform test loads 8/26/2010 9/15/2010
Train agency users 9/17/2010 10/5/2010

 

Requires Awareness:
  • DCS resource is not committed to the project.

Slide 25

BAS – 2682 Inventory Pilot - Department of Mental Health (DMH)

  • Overall Issues Status: Green
  • Project started. DMH currently cleaning up inventory item IDs.
Key Activities
Task Start Finish
Kick-off meeting 3/15/2009 3/15/2009
User Cleanup 3/15/2010 4/30/2010
Conversion Testing 5/1/2010 5/14/2010
User Testing / Training 5/17/2010 6/14/2010
System Configurations and Conversion 6/14/2010 6/30/2010
Go-Live 7/1/2010 7/1/2010

Slide 26

BAS – 2692 Treasury General Ledger Implementation

  • Overall Issues Status: Green
  • Project Kick Off was held April 21
Key Activities
Task Start Fininsh
Prepare for and conduct project kick off 4/12/2010 4/21/2010
Prepare for and conduct and document business process analysis sessions 4/21/2010 4/30/2010
Prepare for and conduct and document fit analysis sessions 5/3/2010 5/27/2010
Define statement of work 5/28/2010 7/2/2010

Slide 27

BAS - 2599 Grants, Projects, Contracts with Accounts Receivable, Billing

Status: The team is in user acceptance testing for statewide and OESC.

 

Key Activities
Task Start Finish
UAT - OESC & Statewide 4/12/2010 4/30/2010
Integration Testing - ODOT (see below) 4/19/2010 5/14/2010
System Roll - OESC 5/3/2010 5/16/2010
Go Live - OESC   5/17/2010
UAT - ODOT TBD TBD

 

Requires Awareness:
  • Go live is scheduled for: OESC - 5/27/2010, on target; ODOT, TBD.
  • Tentative date for starting ODOT Integration Testing was April 19; not yet started.

Slide 28

BAS - 2610 Inventory ODOT 

Status: Integration testing not started.

Key Activities
Task Start Finish
Integration Testing (see below) 4/19/2010 5/14/2010
Prepare for User Acceptance Testing 5/15/2010 5/23/2010
User Acceptance Testing 5/24/2010 6/18/2010
Go Live   TBD

 

Requires Awareness:
  • Integration Testing not started. Testing is still in TST2.

Slide 29

ODOT Phase II Update

Key Activities
Milestone Target Complete
Accelerated OSF/ODOT AR/BI 10/30/2009 10/30/2009
Commitment Accounting 12/14/2010 12/14/2010
Time and Labor Life 1/10/2010 1/10/2010
Leave Conversion 1/10/2010 1/10/2010
Deposits 1/18/2010 1/18/2010
Item Maintenance 1/19/2010 1/19/2010
Bi-Weekly 1/20/2010 01/20/2010
Contracts - County Leasing 4/1/2010 4/1/2010
Asset Management Pilot Rollout TBD  
Inventory TBD  
Grants, Projects, Contracts TBD  
Time & Labor with Project Costing TBD  
Agile Assets TBD  
Manager Self Service - Phase 2 TBD  

Slide 30

Phase II Integration Testing

Open Bugs by Week Ending Date

Statewide / OESC Grants, Projects, Contracts, Accounts Receivable, Billing

Definitions: Block, The functional team is stopped pending resolution; Crash, program will not execute; Major, must be fixed before UAT and Production; Minor, not critical for going live; Feature, nice but not critical for going live.

Week ending 2/27/2010: Block, 1; Major, 2; Tweak, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  integration testing.

Week ending 3/6/2010: Block, 1; Major 3; Tweak, 1 - - Statewide, OESC Grants, Projects, Contracts, AR, Billing  integration testing.

Week ending 3/13/2010: Block, 1; Major 7; Minor, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  integration testing.

Week ending 3/20/ 2010: Block, 3; Major 6; Minor, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  integration testing.

Week ending 3/27/2010: Block, 6; Major 6; Minor, 1; Feature, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  UAT Prep.

Week ending 4/3/2010: Block, 5; Major, 10; Minor, 1; Feature, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  UAT Prep.

Week ending 4/10/2010: Block, 2; Major, 3 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  UAT Prep.

Week ending 4/17/2010: Block, 1; Major; 3; Minor, 1 - Statewide, OESC Grants, Projects, Contracts, AR, Billing  UAT.

Week ending 4/24/2010: Minor, 2; Major, 2 - ODOT integration testing.

Week ending 5/1/2010: Major 2, Minor 2 - ODOT integration testing.

Slide 31

Phase II Integration Bug Trend

Open Bugs on 5/1/2010

Billing: Block, 1.

Human Resources: Major, 1.

Project Costing: Minor, 1.

Payroll: Major, 1.

Time and Labor: Minor, 1.

Slide 32

ODOT Development Requests in Integration Testing, Testing and Development 

Week ending 3/20/2010: Integration Testing, 2; Testing, 9; Development, 26.

Week ending 3/27/2010: Integration Testing, 2; Testing 12; Development, 23.

Week ending 4/3/2010: Integration Testing, 2; Testing 19; Development, 15.

Week ending 4/10/2010: Integration Testing, 2; Testing 19; Development, 17.

Week ending 4/17/2010: Integration Testing, 3; Testing 23; Development, 31.

Week ending 4/24/2010: Integration Testing, 3; Testing 24; Development, 29.

Week ending 5/1/2010: Integration Testing, 3; Testing 41; Development, 12.

Integration testing - 4/19/2010.

Prepare for UAT - 5/15/2010.

UAT - 5/24/2010.

Prepare for and conduct FWHA audit - 5/24/2010

Issue resolution and System Rollout - 6/21/2010.

Go live - 7/3/2010.

Slide 33

Application Enhancement Service Request

August 2009: Pending, 63; Development, 27; User Test, 30; Completed 6.

September 2009: Pending, 58; Development, 35; User Test, 17; Completed, 16.

October 2009: Pending, 56; Development, 33; User Test, 23; Completed, 14.

November 2009: Pending, 64; Development, 36; User Test, 23; Completed, 12.

December 2009: Pending, 54; Development, 47; User Test, 27; Completed, 8.

January 2010: Pending, 59; Development, 42; User Test, 26; Completed, 16. 

February 2010: Pending, 72; Development, 37; User Test, 26; Completed, 9.

March 2010: Pending, 79; Development, 25; User Test, 23; Completed.

April 2010: Pending, 122; Config/Setup, 1; Development, 27; UAT, 16; Completed, 19.

Slide 34

Application Enhancement Service Request Summary - April 2010

(3/26 - 4/30)

  Pending Development Configuration/ Setup User Test Completed
May          
June          
July          
August 63 0 27 30 6
September 58 0 35 17 16
October 56 0 33 23 14
November 64 0 36 23 12
December 54 0 47 27 8
January 59 0 42 24 16
February 72 0 37 26 9
March 79 0 25 23 17
April 122 1 27 16 19

Slide 35

Application Enhancement Service Request Detail - April 2010

(3/26 - 4/30)

 

Problem Mgmt   Pending Config/Setup Dev UAT Completed
CRM 0 0 0 0 0
ELM 0 0 0 0 0
EPM 0 0 0 0 0
FIN 3 0 0 1 1
HCM 5 0 1 6 4
Total 8 0 1 7 5

 

Service Requests   Pending Config Dev UAT Completed
CRM 1 0 2 0 0
ELM 3 0 0 0 1
EPM 1 0 0 0 0
FIN 21 0 12 4 6
HCM 88 1 12 5 7
Total 114 1 26 9 14

 

    Pending Config Dev UAT Completed
Overall Total 122 1 27 16 197

 

Slide 36

Planned Enhancement Service Requests (ESR) On Time Completion

Based on 60-day plan

March 2010 - 2 ESRs not completed; 6 ESRs completed; 5 unplanned ESRs completed.

Slide 37

Program Status

  • Within 10% of plan (green indicator)
  • Within 20% of plan (yellow indicator)
  • Greater than 20% of plan (red indicator)
Project Name Current Project Phase Health Indicator Schedule Project Phase Start Date Project Phase Baseline Completion Project Phase Target Completion Health Indicator Budget
Backfill Developers for Production Support & Enhancements Execution Green 6/15/2009 12/18/2009 6/30/2010 Green
Time & Labor Pilot Execution   3/1/2010 7/31/2010 7/31/2010  
Commitment Accounting Rollout Execution Green 9/1/2009 06/30/2010 6/30/2010 Green
Asset Management Pilot Close Green 6/1/2009 4/14/2010 4/14/2010 Green
Grants, Projects,Contract Accounts Receivable Billing ODOT/OESC Execution   7/1/2010 7/31/2010 7/31/2010  
Time & Labor Manager Self Service ODOT Pilot Execution Green 3/1/2010 7/31/2010 7/31/2010 Green
PeopleSoft Extract Staging Environment Execution Green 1/14/2010 6/18/2010 6/18/2010 Green
Inventory Pilot Department of Mental Health Execution Green 4/15/2010 7/31/2010 7/31/2010 Green
AP Workflow Planning, Execution Green 5/3/2010 7/16/2010 7/16/2010 Green

Slide 38

Program Status

  • Within 10% of plan (green indicator)
  • Within 20% of plan (yellow indicator)
  • Greater than 20% of plan (red indicator)
Project Name Current Project Phase Health Indicator Schedule Project Phase Start Date Project Phase Baseline Completion Project Phase Target Completion Health Indicator Budget
Higher Education Interface Execution Green 4/1/2010 10/31/2011 10/31/2011 Green
HCM Functionality Enhancements Execution Green 1/4/2010 5/28/2010 5/28/2010 Green
Inventory ODOT Execution   3/1/2010 12/31/2010 12/31/2010  
Grants, Projects,Contract Accounts Receivable Billing Commerce, Department of Environmental Quality Execution Green 3/1/2010 12/31/2010 12/31/2010 Green
Business Intelligence - FS Analytics Planning Red 4/1/2009 7/31/2009 7/31/2009 Green
Asset Management Rollout Execution Green 4/19/2010 7/31/2011 7/31/2011 Green
Grants - Provisioning Planning Red 7/31/2008 7/15/2009 5/29/2010 Green
Licensing Planning Red 12/1/2008 8/15/2009 5/15/2010 Green
Treasury General Ledger Implementation Execution Green 4/12/2010 12/31/2010 12/31/2010 Green
Scanning, Barcoding functioning for Phase II Modules Concept          
DCS Vendor Registration Execution Green 12/1/2009 8/31/2010 8/31/2010 Green

Slide 39

Program Status

  • Within 10% of plan (green indicator)
  • Within 20% of plan (yellow indicator)
  • Greater than 20% of plan (red indicator)
Project Name Current Project Phase Health Indicator Schedule Project Phase Start Date Project Phase Baseline Completion Project Phase Target Completion Health Indicator Budget
EFT Remit Advices Execution Green 4/12/2010 6/15/2010 6/15/20108/31/2010 Green
OpenBooks - Phase III Initiation, Planning Green 4/19/2010 5/30/2010 5/30/2010 Green
PeopleTools 8.49 Initiation, Planning Green 3/9/2010 4/30/2010 4/20/2010 Green

Slide 40

Issues

Issue Status
  • Need improved coordination between all Teams (DCS, ODOT, BAS) to get the new items setup, assigned to contracts and PO's.
Project plan has been created.
  • BAS will be involved in the integration testing and UAT. This includes fixing bugs. BAS resources are required to finish the OESC project (live date May 17).
Daily meetings between the CORWE and ODOT project managers are occurring to address project blockers as quickly as possible. Weekly meetings are held to review project issues.
  • DCS resources for the Asset rollout are not committed
We will need to obtain the appropriate resource or re-baseline the project
  • BAS team is supporting an increased number of services. The team does not currently have the capability and capacity to support these services. Current plans include in FY 2011.
Analyze team capability and capacity verses 2011 plans and create a plan to improve self sufficiency.
Last Modified on 03/09/2012