Business Application Services (CORE) Publications - Executive Board Meeting July 21, 2010
The following is a text transcript of the presentation made at the BAS (CORE) Oklahoma Executive Board meeting in July 2010.
Slide 1
BAS Executive Board July 21, 2010
Next CEB Scheduled - August 18, 2010
Slide 2
Agenda
- SQL Requests/Problem Management Summary
- Completed Projects
- Portfolio
- Priority
- Execution Delivery Schedule
- Projects in Movement
- Program Status
- Application Development Service Request Summary
- Scorecard
- Executive Issues
Slide 3
Problem Management
SQL Requests in Total April 2009 to March 2010
| |
July 2009 |
August 2009 |
Sept 2009 |
Oct 2009 |
Nov 2009 |
Dec 2009 |
Jan 2010 |
Feb 2010 |
March 2010 |
April 2010 |
May 2010 |
June 2010 |
| ARBI |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
| CRM |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
| DBA/System |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
2 |
0 |
0 |
| Procurement |
4 |
1 |
5 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
| HRMS |
7 |
24 |
13 |
10 |
3 |
6 |
10 |
12 |
14 |
15 |
11 |
11 |
| Financial |
15 |
14 |
10 |
4 |
14 |
8 |
8 |
6 |
1 |
2 |
7 |
8 |
| EPM |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
| ELM |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
| Purchasing |
0 |
0 |
0 |
0 |
0 |
4 |
8 |
0 |
0 |
2 |
0 |
0 |
Legend
- ARBI - Accounts Receivable/Business Intelligence
- CRM - Customer Relationship Management
- HRMS - Human Resources Management Systems
- EPM - Enterprise Performance Management
- ELM - Enterprise Learning Management
- DBA/System - Database
Slide 4
Problem Management Summary
| Summary |
Total Problems |
Resolved or Resolution in Process |
Investigating |
Resolved by Future Functionality |
DR to be Created |
Monitor |
| Financial |
14 |
8 |
2 |
4 |
0 |
0 |
| PO |
2 |
1 |
1 |
0 |
0 |
0 |
| HCM |
18 |
12 |
1 |
0 |
4 |
1 |
| DBA/System |
3 |
0 |
2 |
0 |
0 |
1 |
| Total |
37 |
21 |
6 |
4 |
4 |
2 |
Slide 5
Completed Project, since last BAS Executive Board
- Commitment Accounting Rollout, Schedule (Green); Budget (Green)
- Backfill Developers, Schedule (Green); Budget (Green)
- Employee Self Service Rollout, Schedule (Green); Budget (Green)
- EFT Remit Advices, Schedule (Green); Budget (Green)
- AP Workflow, Schedule (Green); Budget (Green)
Slide 6
BAS Completed Projects 2010 First and Second Quarters - Total 10
Schedule
- *World Class - 80% on time
- *Median - 70% on time
- 2009 Actual - 75% on time
- 2010 First Quarter - 75% on time
- 2010 Second Quarter - 100% on time
Pie chart showing 10% of Projects are over 20% and 90% are within 10% of Schedule
Budget
- *World Class - 94% on time
- *Median - 85% on time
- 2009 Actual - 92% on time
- 2010 First Quarter - 100% on time
- 2010 Second Quarter - 100% on time
Pie Chart showing 100% of Projects are within 10% of Budget.
Slide 7
Completed Projects 2010 - First and Second Quarters
- Asset Management Pilot, Schedule green, Budget Green
- Commitment Accounting Rollout, Schedule green, Budget Green
- HCM Functionality Enhancements, Schedule green, Budget Green
- EFT Remit Advices, Schedule green, Budget Green
- Backfill Developers, Schedule green, Budget Green
- Time & Labor Self Service - OSF, Schedule red, Budget Green
- ARRA Transparency, Schedule green, Budget Green
- Deposits, Schedule green, Budget Green
- Integrated Item Maintenance, Schedule green, Budget Green
- GPC Pilot OESC, Schedule green, Budget Green
Slide 8
Multi-Agency Business Services Opportunity Map
Images of a flow chart showing opportunities, phase and status for three-year period.
Assets
- 2010
- Asset Management Pilot, close, changed phase.
- 2011
- Asset Management Rollout, execution
- Asset Management, ODOT, execution
- Scanning and bar coding, planning
Supply Chain Management
- 2010
- Integrated Item Maintenance, close
- Inventory Mental Health, execution, close
- 2011
- Inventory Oklahoma Department of Transportation (ODOT), execution
- Inventory Implementation, concept
- 2012
- Inventory Rollout, concept
Financial Management
- 2010
- Deposits, close
- Office of State Finance (OSF)/ODOT Accounts Receivable (AR) Billing, close
- Backfill Developers, close
- Accounts Payable (AP) Workflow, close
- EFT Remittance, execution, close
- Treasury General Ledger, execution,
- Backfill Developers, execution
- 2011
- Apply Bundles 2011, concept
- eBill Pay, initiation
- Expense Module, planning
- Voucher Build, concept
- PCard BOA transition, concept
- 3% Backup Withholdings, concept
- Treasury Module, concept
- 2012
- Financials Upgrade, concept
- P-card Module, concept
Enterprise Service Automation
- 2010
- Grants, Projects, Contracts (GPC) OESC, close
- GPC Pilot, ODOT, execution
- GPC Pilot Oklahoma Department of Corrections (ODOC) and Department of Environmental Quality (DEQ), execution
- 2011
- 2012
Human Capital Management
- 2010
- Time and Labor (T&L) Pilot, execution
- T&L Manager Self Service Pilot, close
- Enterprise Learning Rollout, planning
- Commitment Accounting Rollout, close
- HCM Functionality Enhance, close
- Employee Self Service Rollout, close
- T&L for Non Bi-Weekly, execution
- ODOT T&L MSS, execution
- Higher Education Interface, execution
- 2011
- T&L Manager Self Service Rollout, concept
- Apply Bundles 2011, concept
- T&L Rollout, initiation
- Leave Request Approval, concept
- Organization Publisher, initiation
- 2012
- Apply Bundles, concept
- E-Performance, concept
Other
- 2010
- Licensing, planning
- ARRA Transparency, close
- Grants Provisioning, planning
- Data Staging Area, close
- OpenBooks Phase 3, planning
- PeopleTools 8.49, execution
- 2011
- Business Inteligence Financial Analytics, planning
- Archiving Phase 2, concept
- FFATA Transparency, concept
- Governmental Risk and Compliance, concept
- 2012
- Training Web Delivery, concept
- Address Scrubbing Software, concept
- Budget, concept
- Portal - PeopleSoft Sign on, concept
Supplier Relationship
- 2010
- Vendor Registration, execution
- Strategic Sourcing - e-Supplier Rollout, concept
- 2011
Slide 9
Portfolio Priority 1-15
| Project Name |
Project Manager |
Dept |
Function |
Current Project Phase |
Priority within Function |
| Backfill Developers for Production Support and Enhancements |
Fred Cantrell |
BAS |
Financial Mgmt + Human Capital Mgmt |
Planning, Execution |
1 |
| Time and Labor Pilot/ ODOT |
Alex / Kim |
BAS |
Human Capital Mgmt |
Execution |
2 |
| Inventory Pilot Department of Mental Health |
Alex / Kim |
BAS |
Supply Chain Management |
Execution |
3 |
| Department of Central Services Vendor Registration |
Lisa McKeithan |
BAS |
Supply Chain Management |
Execution |
4 |
| P-Card - BOA Transition |
Lisa McKeithan |
BAS |
Financial Management |
Initiation |
5 |
| GPC, A/R, Billing, T&L Extended Departments of Commerce (Commerce) and Environmental Quality (DEQ) |
Alex / Kim |
BAS |
Enterprise Service Automation |
Execution |
6 |
| Higher Education Interface |
Lisa McKeithan |
BAS |
Human Capital Management |
Execution |
7 |
| PeopleTools 8.49 |
Mike Jorski |
AppDev |
BAS FIN, CRM, EPM |
Execution |
8 |
| Inventory - ODOT |
Alex / Kim |
BAS |
Supply chain management |
Execution |
9 |
| Assets - ODOT |
Alex |
BAS |
Financial management |
Planning, Execution |
10 |
| GPC - ODOT |
Alex / Kim |
BAS |
Enterprise Service Automation |
Execution |
11 |
| T&L Manager Self Service ODOT Pilot |
Alex / Kim |
BAS |
Enterprise Service Automation |
Execution |
12 |
| Treasury General Ledger Implementation |
Alex |
BAS |
Financial management |
Execution |
13 |
| PeopleSoft Extract Staging Environment |
Lisa McKeithan |
BAS |
Other |
Planning |
14 |
| Business Intelligence Financial Analytics |
Lisa McKeithan |
BAS |
Other |
Planning |
15 |
Slide 10
Portfolio Priority 14-26
| Project Name |
Project Manager |
Dept |
Function |
Current Project Phase |
Priority within Function |
| OpenBooks - Phase III |
Lisa McKeithan |
BAS |
Other |
Planning, Execution |
16 |
| Asset Management - Rollout |
Michael Grisser |
BAS |
Assets |
Execution |
17 |
| Travel & Expense EFT |
Steve Wilson |
DCAR |
Financial Management |
Execution |
18 |
| Grants - Provisioning |
Lisa McKeithan |
BAS |
Other |
Planning |
19 |
| Licensing |
Lisa McKeithan |
BAS |
Other |
Planning |
20 |
| Enterprise Learning Management - Rollout |
Michael Grisser |
BAS |
Human Capital management |
Planning, Execution |
21 |
| Scanning and Bar-coding for Phase II modules |
Alex |
BAS |
Assets |
Concept |
22 |
| Expense Module |
Alex/Kim |
BAS |
Financial management |
Planning |
23 |
| Budget |
Lisa McKeithan |
BAS |
Other |
Concept, Initiation |
24 |
| eBill Payment |
Lisa McKeithan |
BAS |
Financial Mgmt |
Concept |
|
| Federal Funding Accountability and Transparency Act (FFATA) |
Lisa McKeithan |
BAS |
Accounts Payable |
Concept |
|
| 3% Federal Withholding |
Lisa McKeithan |
BAS |
Accounts Payable |
Concept |
|
Slide 11
Projects in Execution Delivery Schedule
- PeopleSoft Extract Staging Environment - January-June 2010
- Time and Labor Pilot / ODOT - June 2009-July 2010
- GPC, A/R, Billiing / ODOT - July 2009-July 2010
- Inventory ODOT - August 2009-July 2010
- T&L Manager Self Service ODOT - March-August 2010
- Inventory Pilot Department of Mental Health - April-July 2010
- DCS Vendor Registration - December 2009-August 2010
- PeopleTools 8.49 - September 2010
- Assets ODOT - September-November 2010
- GPC, A/R, Billing, T&L Extended / Commerce/DEQ - March-December 2010
- Treasury GL Implementation - April-December 2010
- OpenBooks - Phase III - May-December 2010
- FY11 Technical Backfill - July 2010-June 2011
- ELM Rollout - May 2010-July 2011
- Asset Management Rollout - August 2010-July 2011
- Higher education interface - April 2010-October 2011
Slide 12
Detailed Milestone Plan, BAS - 2676 OpenBooks Phase III
Design and build the OpenBooks data warehouse and website. New design must include improved search functionality including detailed vendor payments, dashboard look and feel and download capabilities.
Milestone Plan (+/- 10%)
- Design and Build Extracts to Data Staging Environment. (Task, May-June 2010)
- Design/Model Data Warehouse and Repository. (Task, May-July 2010)
- Reports and Testing. (Task, June-October 2010)
- OK.gov Integration; Automate Uploads & Documentation. (Task, October-December 2010)
- Deploy - ARRA (Milestone, September 2010)
- Deploy - Open Books. (Milestone, December 2010)
Issues
- Financials Analytics will not start until after this project is completed.
- Any delay in the AP Workflow project will impact this schedule.
- New legislation (SB2310/SB1759) will require changes to the current timeline and cost.
- Included ARRA updates due 9/28/2010.
Slide 13
Detailed Milestone Schedule, BAS - 2801 FY11 Technical Backfill AppDev
Backfill Developers for Enhancement Service Requests.
Milestone Schedule (+/- 10%)
- FIN, EPM Production support and required enhancements. (July 2010-June 2011)
- HCM, ELM, CRM production support and required enhancements. (July 2010-June 2011)
Issues
- This is for technical backfill services for Enhancement Service Requests and 30-day post go-live support.
- External backfill staff will be targeted to FIN and HCM.
- External Backfill staff could be applied to CRM, ELM & EPM as needed.
- This plan assumes state technical resources average four hours per day to assist and coordinate external resource activities.
Slide 14
Detailed Milestone Plan, BAS - 2637 Enterprise Learning Management Rollout
Phase II Rollout of Enterprise Learning Management Group A consists of Department of Career and Technology Education (800), CompSource Oklahoma (390), Department of Transportation (345), Administrative Office of the Courts (199, 219, 220 and 677), Oklahoma.
Milestone Plan (+/- 10%)
- Business Process Review and Kickoff. (Task, August-September 2010)
- Setup for Agencies/Update additional HCM fields. (Task, September 2010-April 2011).
- Verify Configuration. (Task; Group A, September-October 2010; Group B, November-December 2010; Group C, January-February 2011)
- Testing - Includes data entry for learners catalog, etc. (Task; Group A, October-November 2010; Group B, December 2010-January 2011; Group C, February-March 2011)
- Business Process Testing. (Task; Group A, October-November 2010; Group B, December 2010-January 2011; Group C, March-April 2011)
- Train Users. (Task; Group A, October-November 2010; Group B, December 2010-January 2011; Group C, March-April 2011)
- Go-live. (Milestone; Group A, November 30, 2010; Group B, January 31, 2011; Group C, April 30, 2011)
- Convert Agency Training History. (Task, December 2010-June 2011)
- Post Production Support. (Task, December 2010-July 2011.)
Issues
- Need to determine if update of additional HCM fields will be manual or load.
- Will we require enrollment to go through a nominating official or employee self enrol?
- To meet the timelines, all Groups must take the system as it is currently designed/configured.
- Additional functionality requirements will not be met in this rollout and may require a consultant and additional technical support (Phrase III).
Group A - 5,000 employees (8/1/2010 - 11/30/2010 - 12/31/2010)
Group B - 2,250 employees plus HRDS courses (11/1/2010 - 1/31/2011 - 3/31/2011)
Group C - 500 employees plus CPO's, CPA's, Financial Managers and Firefighters statewide (1/20/2011 -4/30/2011 - 6/15/2011)
Slide 15
Detailed Milestone Plan, 2800 - Pcard - Bank of America Transition
Design and build the OpenBooks data warehouse and website. New design must include improved search functionality including detailed vendor payments, dashboard look and feel and download capabilities.
Milestone Plan +/- 50%
- Define requirements with BOA. (Task, May-July 2010)
- Development and Testing. (Task, August-October 2010)
- Integration Testing with BOA. (Task, October-November 2010)
- Implementation. (Milestone, November 30, 2010.)
Issues
- One outbound interface: GL Exports.
- Two inbound interfaces: Vouchers, 1099s and OpenBooks.
Slide 16
Detailed Milestone Schedule, 2810 - Asset Management - ODOT
Asset Management Implementation - ODOT
Milestone Schedule
- Prepare for integration testing. (August 2009)
- Perform integration testing. (August-September 2009)
- Prepare for User Acceptance Testing. (September-October 2009)
- Perform User Acceptance Testing. (October 2009)
- Perform System Roll-out / Conversion. (November 2009)
- Go-Live. (November 30, 2009)
- Production support. (December 2009)
Slide 17
Detailed Milestone Schedule - BAS Expense Evaluation
The project will create a working prototype from which we will evaluate whether Expenses is a useful and viable solution for the state.
Milestone Schedule +/- 50%
- Gather initial requirements from OSF. (July 2010)
- Define scope of the Expense implementation. (July 2010)
- Conduct a high-level FIT/Gap. (July 2010)
- Create a working prototype using OSF requirements and data. (July-August 2010)
- Evaluate results and determine next steps. (July-August 2010)
- Develop a +/- 10% Plan. (July-August 2010)
- Decision - Next steps. (mid-August 2010)
Issues
- BPA Questionnaire created and sent to Steve Wilson.
- Response received.
- Meeting scheduled for 7/15.
- Configuration has begun in FSPH2.
Slide 18
Program Status
HCM
Slide 19
BAS – 1080 Higher Education Payroll
- Status: Green
- Convert higher education agencies from the legacy payroll system to the PeopleSoft system.
Key Activities
| Task |
Start |
Finish |
| PY Test Scripts |
7/1/2010 |
7/31/2010 |
| HR Interface Testing |
7/5/2010 |
7/31/2010 |
| PY Conversion extract verification |
7/16/2010 |
7/31/2010 |
| PY Conversion/Interface Testing |
8/1/2010 |
9/30/2010 |
| Requires Awareness: |
- Working on project plan to include state specific tasks.
- OU time is limited during August/September during enrollment.
|
Slide 20
BAS – 2581 Time and Labor
- Status: Red
- This project is to address Time & Labor functionality for bi-weekly agencies. The pilot agencies are OESC and ODOT. OESC went live on schedule May 17.
| Requires Awareness: |
- Integration and User Acceptance Testing for ODOT will be scheduled to coincide with a re-baselined plan.
|
Slide 21
BAS – 2666 Grants, Projects, Contracts with AR/Billing Monthly Extended Time & Labor
- Status: GREEN
- The Team is performing Prototype Sessions with DEQ and Commerce for implementation of the Phase II modules.
Key Activities
| Task |
Start |
Finish |
| Prototype Review and Documentation |
6/14/2010 |
7/9/2010 |
| Develop 7 Unit Test (Rules, Conversions, Interfaces & Modifications) |
6/7/2010 |
8/6/2010 |
| Define and Test Security Roles |
7/12/2010 |
7/23/2010 |
| Prepare for Integration Testing |
7/19/2010 |
8/6/2010 |
Slide 22
Program Status
Financials
Phase II Modules
Slide 23
BAS – 2611 PeopleTools 8.49
- Status: GREEN
- Upgrade EPM to PeopleTools version 8.49.
Key Activities
| Task |
Start |
Finish |
| Prepare Change Assistance & Stage Software |
8/30/2010 |
8/31/2010 |
| Upgrade & test non-prod EPM environments |
9/10/2010 |
9/24/2010 |
| Upgrade EPM production environment |
9/25/2010 |
9/25/2010 |
| Upgrade EPM development environment |
9/27/2010 |
9/28/2010 |
| Requires Awareness: |
- Execution starts the end of August.
- CRM PeopleTools will be upgraded with the CRM ITIL project.
- FIN PeopleTools will be upgraded with the next maintenance pack project.
|
Slide 24
BAS - 2675 Data Staging Environment
- Status: Red
- Build staging environment containing PeopleSoft Extracts that will be used by ODOT.
Key Activities
| Task |
Start |
Finish |
ODOT Access |
| Phase I extracts (6) signed off by ODOT |
|
7/2/2010 |
|
| Assets (0523) & Projects (0514) have been re-migrated to FSTST2 and is ready for functional testing. |
6/25/2010 |
7/12/2010 |
7/12/2010 |
| Contracts (0513) & Billing (0512) still working on updating programming |
6/25/2010 |
7/31/2010 |
7/31/2010 |
| Sign-off on Phase Modules |
|
8/15/2010 |
7/31/2010 |
| Inventory - define requirements |
7/1/2010 |
7/23/2010 |
|
| Inventory - programming |
7/1/2010 |
8/15/2010 |
8/22/2010 |
| Sign-off on Inventory |
|
8/31/2010 |
8/22/2010 |
| Requires Awareness: |
- Interfaces/batch process were not updating audit tables and getting records created in the staging tables. Re-work required on Phase II extracts (db trigger).
- Request to add inventory information.
|
Slide 25
BAS - 2681 DCS Vendor Registration
- Status: Green
- Build interfaces between ok.gov and PeopleSoft for validation and upload of vendor bidder data into PeopleSoft.
Key Activities
| Task |
Start |
Finish |
| Go-live with vendor registration - Part 1 |
|
7/19/2010 |
| Development/Testing - Tech Specs 0027 - update 'look-up' functionality within PeopleSoft to include bidders |
6/4/2010 |
8/31/2010 |
| Development/Testing - Bidder to Vendor Update |
5/10/2010 |
8/31/2010 |
| Review/Revise process - OSF & DCS |
7/31/2010 |
7/31/2010 |
| Requires Awareness: |
- Missed Phase I implementation by 19 days.
- DCS is working on Phase II for updated front-end. This will cause some reprogramming of the interface that will be tracked as a service request. Scheduled for the fall.
|
Slide 26
BAS - Asset Management Rollout
- Status: Green
- Meetings to be held to prepare for Kickoff Session. Will not make much progress until August after the DMH Inventory Implementation is completed, consulting resources are filled and DCS participation is resolved.
Key Activities
| Task |
Start |
Finish |
| Prepare for and conduct project kickoff |
TBD |
TBD |
| Configure and verify agency conversion data |
8/16/2010 |
11/5/2010 |
| Perform test Loads |
9/26/2010 |
10/15/2010 |
| Train agency users |
10/17/2010 |
11/05/2010 |
| Requires Awareness: |
- DCS resource is not committed to the project - Brenda is addressing. If no DCS resource, rollout plan may need to be adjusted.
- Patricia not available until August.
- Brenda to also assist with agency buy in to rollout plan.
- Lost consulting resource; took another assignment - will delay start and could impact ODOT assets.
- ODOT assets require re-baselining of rollout timeline.
|
Slide 27
BAS - 2682 Inventory Pilot - DMH
- Status: Green
- The following warehouses are in production:
- Griffin Memorial Hospital
- Carl Albert Community Mental Health Center
- Bill Willis Community Mental Health Center
Key Activities
| Task |
Start |
Finish |
| Go-live |
7/1/2010 |
7/6/2010 |
| Post Production Support |
|
|
| Requires Awareness: |
- Working with DMH to cleanse data for the remaining warehouses:
- Jim Taliaferro Community Mental Health Center
- Oklahoma Forensic Center
- Northwest Center for Behavioral Health
|
Slide 28
BAS - 2692 Treasury GL Implementation
- Status: Green
- The team conducted the Fit Analysis Sessions and has reviewed the notes. They are in the process of identifying final approach and impacts.
Key Activities
| Task |
Start |
Finish |
| Create decision approach papers |
5/28/2010 |
7/2/2010 |
| Identify development requirements |
5/28/2010 |
7/2/2010 |
| Configuration |
7/6/2010 |
7/13/2010 |
| Define security |
7/17/2010 |
7/16/2010 |
| Requires Awareness: |
- Office of the State Treasurer has requested that their go-live date be moved to a month-ender. Rather than go live on 11/15/2010 they would like to look at either 10/31/10 or 12/31/2010.
|
Slide 29
BAS - 2599 Grants, Projects, Contracts with AR/Billing
- Status: Red
- This project is on hold.
Key Activities
| Task |
Start |
Finish |
| Functional Unit Testing - ODOT (see below) |
|
|
| Requires Awareness: |
- ODOT cannot supply a date for conversion of legacy data.
|
Slide 30
BAS - 2610 Inventory ODOT
Key Activities
| Task |
Start |
Finish |
| Integration Testing |
|
|
| Prepare for User Acceptance Testing |
|
|
| User Acceptance Testing |
|
|
| Go Live |
|
|
Slide 31
BAS - 2674 Manager Self Service ODOT/Pilot
- Status: Red
- Project was planned in two phases: (1) limited salary personnel April 24 (complete) and (2) all non Agile Asset personnel to coincide with ODOT GPC go-live date - on hold.
Key Activities
| Task |
% Completed |
Start |
Finish |
| Go-live Limited Pilot - complete |
100 |
4/24/2010 |
4/24/2010 |
| Requirements - Full implementation - Complete |
100 |
3/23/2010 |
4/7/2010 |
Slide 32
Application Enhancement Service Requests
- August 2009 - Pending, Tech, 63; Development, Tech, 27; UAT, Tech 30; Closed, Tech, 6.
- September 2009 - Pending, Tech, 58; Development, Tech, 35; UAT,Tech, 17; Closed, Tech, 16.
- October 2009 - Pending, Tech, 56; Development, Tech, 33; UAT, Tech, 23; Closed, Tech, 14.
- November 2009 - Pending, Tech, 64; Development, Tech, 36; UA,T Tech, 23; Closed Tech, 12.
- December 2009 - Pending, Tech, 54; Development, Tech, 47; UA, Tech, 27; Closed, Tech, 8.
- January 2010 - Pending, Tech, 59; Development, Tech, 42; UAT, Tech, 24; Closed, Tech, 16.
- February 2010 - Pending, Tech, 72; Development, Tech, 37; UAT Tech, 26; Closed, Tech, 9.
- March 2010 - Pending, Tech, 79; Development, Tech, 25; UAT, Tech, 23 ; Closed, Tech, 17.
- April 2010 - Pending, Tech 122 ; Development, Tech, 27; UAT, Tech, 16 ; Closed, Tech, 19.
- May 2010 - Pending, Tech, 125; Development, Tech, 22; UAT, Tech 18 ; Closed, Tech 22.
- June 2010 - Pending, Tech, 87, Function, 37; Development, Tech, 22, Function, 1; UAT, Tech, 11, Function 1; Closed, Tech, 13, Function, 10.
Slide 33
Current Application Enhancement Service Requests - June 2010
(5/29 - 6/30)
| Functional ESRs |
|
Pending |
Config/Setup |
UAT |
Completed |
| CRM |
0 |
0 |
0 |
0 |
| ELM |
0 |
0 |
0 |
0 |
| EPM |
0 |
0 |
0 |
0 |
| FIN |
3 |
0 |
0 |
0 |
| HCM |
34 |
1 |
1 |
10 |
| Total |
37 |
1 |
1 |
10 |
| Technical ESRs |
|
Pending |
Dev |
UAT |
Completed |
| CRM |
1 |
3 |
0 |
0 |
| ELM |
3 |
0 |
0 |
0 |
| EPM |
1 |
0 |
0 |
0 |
| FIN |
27 |
7 |
4 |
4 |
| HCM |
55 |
12 |
7 |
9 |
| Total |
87 |
22 |
11 |
13 |
| |
|
Pending |
Dev |
UAT |
Completed |
| Total |
124 |
23 |
12 |
23 |
Slide 34
Planned Enhancement Service Requests On-Time Completion Based on 60-Day Plan
- March - 6 ESRs completed; 2 not completed; 5 unplanned completed.
- May - 3 ESRs completed; 5 not completed; 4 unplanned completed.
Slide 35
BAS Scorecard
- Within 10% of plan (green indicator)
- Within 20% of plan (yellow indicator)
- Greater than 20% of plan (red indicator)
| Project Name |
Current Project Phase |
Health Indicator Schedule |
Project Phase Start Date |
Project Phase Baseline Completion |
Project Phase Target Completion |
Health Indicator Budget |
| FY11 Technical Backfill |
Planning,Execution |
Green |
7/1/2010 |
6/30/2010 |
6/30/2010 |
Green |
| Time and Labor Pilot/ODOT |
Execution |
Red |
3/1/2009 |
7/31/2010 |
7/31/2010 |
Red |
| Inventory Pilot Department of Mental Health |
Execution |
Green |
4/15/2010 |
7/31/2010 |
7/31/2010 |
Green |
| DCS Vendor Registration |
Execution |
Green |
12/1/2009 |
8/31/2010 |
8/31/2010 |
Green |
| P-Card - BOA Transition |
Initiation, Planning |
Green |
5/1/2010 |
8/15/2010 |
8/15/2010 |
Green |
| Grants, Projects,Contract Accounts Receivable Billing ODOT/OESC |
Execution |
Green |
03/01/2010 |
12/31/2010 |
12/31/2010 |
Green |
| Higher Education Interface |
Execution |
Green |
4/1/2010 |
10/31/2010 |
10/31/2010 |
Green |
| PeopleTools 8.49 |
Execution |
Green |
8/30/2010 |
9/28/2010 |
9/28/2010 |
Green |
| Inventory ODOT |
Execution |
Red |
8/1/2009 |
7/31/2010 |
7/31/2010 |
Red |
| Assets ODOT |
Planning, Execution |
Green |
8/1/2010 |
11/15/2010 |
11/15/2010 |
Green |
| Grants, Projects, Contract A/R Billing, ODOT |
Execution |
Red |
7/1/2009 |
7/31/2010 |
7/31/2010 |
Red |
| T&L Manager Self Service ODOT |
Execution |
Red |
3/1/2010 |
7/31/2010 |
7/31/2010 |
Red |
Slide 36
Program Status
- Within 10% of plan (green indicator)
- Within 20% of plan (yellow indicator)
- Greater than 20% of plan (red indicator)
| Project Name |
Current Project Phase |
Health Indicator Schedule |
Project Phase Start Date |
Project Phase Baseline Completion |
Project Phase Target Completion |
Health Indicator Budget |
| Treasury GL Implementation |
Execution |
Green |
4/12/2010 |
12/31/2010 |
12/31/2010 |
Green |
| PeopleSoft Extract Staging Environment |
Execution |
Red |
1/14/2010 |
6/18/2010 |
8/31/2010 |
Green |
| Business Intellignece - FS Analytic |
Execution |
Red |
4/1/2009 |
7/31/2009 |
7/31/2010 |
Green |
| OpenBooks - Phase III |
Execution |
Green |
6/1/2010 |
12/31/2010 |
12/31/2010 |
Green |
| Asset Management Rollout |
Execution |
Green |
4/19/2010 |
8/31/2010 |
8/31/2010 |
Green |
| Licensing |
Execution |
R |
12/1/2008 |
8/15/2009 |
7/31/2010 |
Green |
| ELM Rollout |
Execution |
Green |
8/1/2010 |
7/31/2011 |
7/31/2011 |
Green |
| Scanning and Barcoding functionality for Phase II Modules |
Execution |
|
|
|
|
|
| Expense Module |
Execution |
Green |
7/12/2010 |
8/20/2010 |
8/20/2010 |
Green |
Slide 37
Issues
| Issue |
Status |
| (1) ODOT Phase II (Projects, Grants, AR, Billing Inventory) will not meet their July 3 scheduled implementation date. |
ODOT cannot supply an estimated date when they will have the legacy data converted into PeopleSoft. The project is on hold until this data is provided. |
| (2) The Asset consultant left the project without conducting turnover to a new consultant. |
Maximus is looking for an Asset consultant. They have committed that they will supply the necessary resource so that ODOT Assets and Asset rollout dates are met. Any consulting resources required over our plan will not be billed to the state. |
| (3) The fixed asset rollout plan has been completed and and additional state resource is required to deliver on the current schedule. |
Initial meeting held with DCS to obtain resources. No follow up meeting has occurred. Do we need to postpone this project? |
| (4) Commerce will be going live on Phase 2 without a Grants Provisioning. They will utilize manual work-arounds until we acquire a Grants provisioning package. |
We need to expedite the Grants provisioning purchasing process and prioritize Commerce in the first implementation. |
Slide 38
Issues
| Issues |
Status |
| (5) We need to determine which agencies will be moved to Phase 2 after Commerce and DEQ. |
The additional agencies will be scheduled around the ODOT implementation. This project could start as early as November. |
| (6) ODOT has a staff shortage in AR due to turnover of staff. Payments have been posted in error causing aging to be off. Reconciliation of the initial load of County Leases is still in progress. ODOT is not using functionality implemented last October ( Accelerated AR/BI - Outdoor Advertising, Tuition, etc. |
Currently 2 positions are being recruited. Working with Ciber on reconciliation as time permits (required for GAAP). Mark will continue support on County Leases and Deposits until new hires come on. Mark will have to train staff when hired. |