FACILITIES SERVICES PROJECTS
This list is updated frequently, Please check back often for current information - updated 07/07/2010.
| Funded - Working Projects |
| Building |
Project |
Notes |
| Agriculture |
Domestic water heater installation |
Material has been ordered and work is scheduled to begin 074/07/10 |
| DOT |
Snack bar renovation |
Contractor demolition of smoke room is complete. Framing of new office walls began 4/21. This project is now at 75% completion. |
| DOT |
Window Tinting |
Project is at 35% complete |
| Courts |
DDC Controls - Programming/Graphics |
Boiler programming to be completed week of 07/09/10 |
| Courts |
Roof Replacement |
Currently in design phase |
| Capitol |
Acquisition of 41 heat pumps |
Received completed PO and pumps on order. 5/20/10 |
| Capitol |
Installation of heat pumps |
Waiting on arrival and will be scheduled for in house installation. |
| Capitol |
Cooling tower basin heaters and insulation |
Johnson Controls tested the all heat tapes and found them operating correctly. Heat tapes are being re-insulated. JCI will have to wait for cooler weather to install new heaters in basin. |
| Connors |
Computer room conversion to chilled water |
There was a pre construction meeting on June 23rd at the site. They started the prep work for the project on the 28th. Should be in full swing next week. |
| Hodge |
VSD for building water pump installation |
Installation is to be scheduled. |
| LEED/CAP |
landscape installation |
The stone and rock that we called for in the specs has not arrived at Myers yard as of yet but they expect it next week. |
| Library |
Design for lighting renovation |
Design for relocation of lighting is complete. 25 Watt bulbs ordered. Reid & Reid Electrical started the relocation of lights 6/30/10 |
| Park |
Oil Derrick Fencing |
Requisition and P.O. have been approved and sent out for bid |
| Park |
Central Bed Landscaping (WR/Seq) |
95% Complete |
| Tulsa |
Air Handling Unit upgrade |
Proposal under review |
| Will Rogers/ Sequoyah |
Engineering Boiler Replacement |
Engineering is complete. Abatement is complete and boilers installation was started 7/7/10. |