Oklahoma, www.OK.gov Department of Central Services Home Page

Skip Nav Skip to Search
 |  Make a Reservation



Facilities Management Projects 

This list is updated frequently, Please check back often for current information - updated 06/27/2008.

Building Project Status
Agriculture, Connor's,
Hodge, Library, ODOT, Sequoyah, Tulsa, Will Rogers
Generator Replacements All new generators are in place. Start ups and final testing still to be completed.
Agriculture New Laboratory Building All floors & roof have been poured. All trades on site. Mechanical duct second & third floor installed. Main fire line and branch lines run on second & third floors. Equipment pads have been poured. Roofers scheduled to begin the 28th.
All DCS Managed Buildings Maintenance Software  Harold continues with the development of the hierarchy for database.
All DCS Managed Buildings Facility Condition Assessment  Held webinar with VFA on June 23rd to review some of the report data. Analyzing data and development of long term deferred maintenance plan just beginning.
Bank Building Banking Commission On schedule for final on July 12th. Interior finishes, cabinetry, flooring, painting, continue. Building power has been established by OG&E.
Capitol Replacing Cooling Tower Design documents complete.
C & P HVAC System Redesign Design documents complete. Under final review by Facilities.
Connor's 5th Floor Renovation Bids closed and accepted. JL Walker was accepted bid. Notice of acceptance was processed by Facilities to the CPO on June 23rd.
Connor's 3rd Floor Renovation On hold due to Tax Commission funding setbacks.
Connor's South Emergency Egress Contract has been awarded. Materials have been ordered by Metro Glass. 5-6 week lead time on materials.
Connor's / Hodge AHU Damper repairs Installation of new dampers is complete at both buildings. . Installation of the new DDC controllers and programming continue.
Denver Davison Cooling Tower Replacement On hold design fee under review by Facilities.
Denver Davison Boiler Drafting Design at 95% and being reviewed by Facilities staff.
 Hissom Asbestos Abatement - 4 Buildings Report received from High Plains. Only remaining asbestos identified in the report is some 9” floor tile and it’s mastic.
 Hodge Freight Elevator Repair Contractor still waiting on delivery of all materials. Scheduled to begin work first week of July.
 Jim Thorpe Access system for loading dock and freight elevator Rodney continues working with tenant agencies in completing access control forms. Training on system operation and badge creation has been taking place.
 Jim Thorpe Cooling Tower Replacement Design fee under review by Facilities.
 Jim Thorpe Controls Design Design fee requested by Facilities.
 Library Bay Lighting Control Design is at 95%. Awaiting final electrical drawings.
 Mansion Heating System Redesign Design completed. Secondary options being discussed for Greening of the Mansion.
 Mansion Cooling & Air System Awaiting completion of design documents.
ODOT Freight elevator Room Partition Design complete. Under review by Facilities.
ODOT Overhead Doors, Garage Area Design complete. Under review by Facilities.
 Parks New fence (Oil Derrick South Entrance Dave has final plans & is working on value engineering.
 Sequoyah Upgrade Access System  Personnel information being programmed, card design being developed.  Once these items are complete, new cards can be created & the system will be operational.
Tulsa Floor Tile Replacement Ceramic tile installation on-going. Joe has received considerable positive feedback from building tenants.
 Will Rogers Replacement of Access System Installation complete. Loading user information. Personnel information will be loaded next week
 Will Rogers Snack Bar Renovation  Facilities staff has begun demolition of the area. Waiting further design instructions from DRS
 Will Rogers Lobby  Fee proposal accepted. Design work being prepared
 Will Rogers Floor tile replacement in basement & tunnel halls Tunnel area and ramp complete. Due to other commitments this project is on temporary hold.