| Building |
Project |
Status |
Agriculture, Connor's,
Hodge, Library, ODOT, Sequoyah, Tulsa, Will Rogers |
Generator Replacements |
All new generators are in place. Start ups and final testing still to be completed. |
| Agriculture |
New Laboratory Building |
All floors & roof have been poured. All trades on site. Mechanical duct second & third floor installed. Main fire line and branch lines run on second & third floors. Equipment pads have been poured. Roofers scheduled to begin the 28th. |
| All DCS Managed Buildings |
Maintenance Software |
Harold continues with the development of the hierarchy for database. |
| All DCS Managed Buildings |
Facility Condition Assessment |
Held webinar with VFA on June 23rd to review some of the report data. Analyzing data and development of long term deferred maintenance plan just beginning. |
| Bank Building |
Banking Commission |
On schedule for final on July 12th. Interior finishes, cabinetry, flooring, painting, continue. Building power has been established by OG&E. |
| Capitol |
Replacing Cooling Tower |
Design documents complete. |
| C & P |
HVAC System Redesign |
Design documents complete. Under final review by Facilities. |
| Connor's |
5th Floor Renovation |
Bids closed and accepted. JL Walker was accepted bid. Notice of acceptance was processed by Facilities to the CPO on June 23rd. |
| Connor's |
3rd Floor Renovation |
On hold due to Tax Commission funding setbacks. |
| Connor's |
South Emergency Egress |
Contract has been awarded. Materials have been ordered by Metro Glass. 5-6 week lead time on materials. |
| Connor's / Hodge |
AHU Damper repairs |
Installation of new dampers is complete at both buildings. . Installation of the new DDC controllers and programming continue. |
| Denver Davison |
Cooling Tower Replacement |
On hold design fee under review by Facilities. |
| Denver Davison |
Boiler Drafting |
Design at 95% and being reviewed by Facilities staff. |
| Hissom |
Asbestos Abatement - 4 Buildings |
Report received from High Plains. Only remaining asbestos identified in the report is some 9” floor tile and it’s mastic. |
| Hodge |
Freight Elevator Repair |
Contractor still waiting on delivery of all materials. Scheduled to begin work first week of July. |
| Jim Thorpe |
Access system for loading dock and freight elevator |
Rodney continues working with tenant agencies in completing access control forms. Training on system operation and badge creation has been taking place. |
| Jim Thorpe |
Cooling Tower Replacement |
Design fee under review by Facilities. |
| Jim Thorpe |
Controls Design |
Design fee requested by Facilities. |
| Library |
Bay Lighting Control |
Design is at 95%. Awaiting final electrical drawings. |
| Mansion |
Heating System Redesign |
Design completed. Secondary options being discussed for Greening of the Mansion. |
| Mansion |
Cooling & Air System |
Awaiting completion of design documents. |
| ODOT |
Freight elevator Room Partition |
Design complete. Under review by Facilities. |
| ODOT |
Overhead Doors, Garage Area |
Design complete. Under review by Facilities. |
| Parks |
New fence (Oil Derrick South Entrance |
Dave has final plans & is working on value engineering. |
| Sequoyah |
Upgrade Access System |
Personnel information being programmed, card design being developed. Once these items are complete, new cards can be created & the system will be operational. |
| Tulsa |
Floor Tile Replacement |
Ceramic tile installation on-going. Joe has received considerable positive feedback from building tenants. |
| Will Rogers |
Replacement of Access System |
Installation complete. Loading user information. Personnel information will be loaded next week |
| Will Rogers |
Snack Bar Renovation |
Facilities staff has begun demolition of the area. Waiting further design instructions from DRS |
| Will Rogers |
Lobby |
Fee proposal accepted. Design work being prepared |
| Will Rogers |
Floor tile replacement in basement & tunnel halls |
Tunnel area and ramp complete. Due to other commitments this project is on temporary hold. |
| |
|
|